Status:

Submittal of site plan: December 7, 2021 (1st), April 12, 2022 (2nd), June 9, 2022 (3rd), July 12, 2022 (4th), July 29, 2022 (5th), October 25, 2022 (6th), November 29, 2022 (7th), April 3, 2023 (8th), May 28, 2023 (9th)
Submittal of Planned Development: June 20, 2020
Site Plan Review Committee (SPRC) review: December 26, 2021 (1st), April 28, 2022 (2nd), June 23, 2022 (3rd), July 22, 2022 (4th),  August 24, 2022 (5th), November 22, 2022 (6th), December 9, 2023 (7th), May 9, 2023 (8th), DUE June 12, 2023 (9th)
Neighborhood meeting: Required. June 8, 2022
Planning Board: Required.  December 8, 2022
City Commission (1st reading): Required.  May 16, 2023
City Commission (2nd reading): Required.  June 6, 2023


05.26.2023 Site Plan

Site plan sheets submitted 04.03.2023

01.06.2022 Information submitted for January 11, 2023 SPRC meeting regarding 164-unit multi-family development


11.29.2022 Site Plan

11.18.2022 Updates

Site plan submittal, October 25, 2022



Site plan submittal, July 29, 2022


Documents, July 29, 2022

Updated sheets, July 12, 2022

Updated documents, July 12, 2022


Planned Business Development Information, submitted June 29, 2022

Site plan submittal, June 9, 2022


Information submitted April 12, 2022
Documents:

Site Plans:

Information submitted December 6, 2021
Documents:

Site Plan:

Traffic related information: